New Belmont Middle and High School Construction Page

                                                                                                                                                                                                                                                                                          

 pw_boston_belmont_exterior_concord_ave_day UPDATE-small.jpg

For questions or comments, please email BelmontHSConstruction@Gmail.com,

for a listing of team members click here.  If there are questions, please contact

Tony DelGreco with Daedalus Projects which is the Owner's Project Management firm at 781-258-6557.

Belmont logo-07.02.19.png

DroneImages-01.png    Photos.png   Webcam.png      Schedules.png    ProjectFiles.png

 Building Update

August 2020 Work Performed

General

   o  Continued Incorporating COVID-19 Provisions on Site for Safe Work Practices.
   o  Continued MEP/Fire Protection Piping, Conduit, and Ductwork Coordination and Installation.

Civil/Site Work
   o  Completed Geothermal Well Drilling and Piping.
   o  Started Construction of Permanent Roads.

B
uilding A
   o  Completed Exterior Framing, and Sheathing.
   o  Continued Installation of MEP/FP System Rough.
   o  Completed Spray Fireproofing.
   o  Completed Roofing Installation of Air-Vapor Barrier (AVB) and Roof Curbs.
   o  Continued Installation of Classroom Window Frames.
   o  Completed Installation of Waterproofing AVB.
   o  Completed Installation of Stair #1.
   o  Started Installation of Masonry at Façade

Building B
   o  Completed Under-slab Utility Installation.
   o  Continued Interior/Exterior Wall Layout and Top Track Installation.
   o  Continued Exterior Framing.
   o  Continued Sheathing.
   o  Continued Spray Fireproofing.
   o  Continued Roofing Installation of Air-Vapor Barrier (AVB) and Roof Curbs.
   o  Started Installation of Slab on Grade.
   o  Started Installation of Waterproofing AVB.
   o  Started Installation of Classroom Window Frames.
   o  Started Installation of Stair #2.
   o  Started Installation of Elevator Shaft. 

Building C
   o  Continued Under-slab Utility Installation.
   o  Continued Interior/Exterior Wall Layout and Top Track Installation Prior to Spray Fireproofing.
   o  Started Installation of Overhead MEP hangers.
   o  Continued Spray Fireproofing.
   o  Started renovation of pool area.

Field House
   o  Completed Summer 2020 Renovation Work, Including Application of Block Filler, Abatement, and Installation of Overhead MEPs


 Look-Ahead

September 2020 Look-Ahead

General

   o  Continue MEP/FP Coordination.

   o  Continue Incorporating COVID-19 Provisions on Site for Safe Work Practices.

Civil/Site Work

   o  Continue Construction of Permanent Roads.

Building A
   o  Complete Sheathing, and Installation of AVB.
   o  Complete Installation of Ground Floor Window Frames and Temporary Plywood.
   o  Complete Interior Wall Layout and Top Track Installation.
   o  Continue Installation of MEP/FP Components.
   o  Continue Installation of Masonry at Façade.
   o  Start Drywall Installation.
   o  Start Glazing Installation.

Building B
   o  Complete Spray Fireproofing.
   o  Complete Installation of Stair #2
   o  Complete Exterior Wall Framing & Sheathing.
   o  Complete Interior Wall Layout and Top Track Installation.
   o  Complete Roofing Installation of Air-Vapor Barrier (AVB) and Roof Curbs.
   o  Complete Installation of Waterproofing AVB.
   o  Complete Concrete Slab on Grade Placements.
   o  Complete Installation of Elevator Shaft.
   o  Complete Installation of Early Walls.
   o  Continue Installation of MEP/FP Components.
   o  Complete Installation of Classroom Window Frames and Temporary Plywood.

Building C

   o  Start Concrete Slab on Grade Placements.
   o  Continue Installation of Roofing Materials.
   o  Continue Installation of AVB.
   o  Continue Installation of Exterior Framing and Sheathing.
   o  Continue Installation of Early Walls.
   o  Complete Spray Fireproofing.
   o  Complete Under-slab Utility Installation (Pending Variance).
   o  Continue Installation of MEP/FP Components.
   o  Continue Renovation of Pool Area.



BHS_Logistics_201903025 reduced (1) Page 001.jpg