Skanska's Preventative Actions for Major Weather Events.  The project's Inclimate Weather & Lighting Policy can be found in "Project Files":

  • Review all ongoing exterior construction activities to ensure all workers, equipment and activities are able to still take place throughout inclement weather
  • If not, stop work temporarily or until weather event has ended and safe to resume work
  • Conduct a thorough review of the project site perimeter fencing to ensure stability and safety adjacent to any publicly accessible areas
  • Ensure that all erosion controls around Clay Pit Pond are intact and repaired if necessary
  • Ensure all silt containment at all permanent and temporary storm drain basins are operation, and clear for proper drainage and protection of system
  • Secure all loose materials around project site, including any elevated loading dock and roofing areas
  • Store and protect all permanent project exterior materials (glass, siding, etc) to be installed in a safe area
  • Compact and/or remove all dumpster debris to avoid loose construction trash from being impacted by high winds
  • Maintain any open contact with Town Public Safety officials if necessary

For a listing of team members click here.  If there are questions, please contact

Tony DelGreco with CHA which is the Owner's Project Management firm at 781-258-6557.


Trucking/Delivery Route:

2021 BMHS Summer Delivery Route.jpg


Belmont logo-07.02.19.png

DroneImages-01.png    Photos.png   Webcam.png      Schedules.png    ProjectFiles.png

Building Update

March 2023 Work Performed


Phase 1

  • Geothermal flushing operation

Phase 2 Site Work and Utilities
  • Continued installing sidewalks
  • Continued raising grade via existing material
  • Continued final grading athletic fields
  • Continuted installing drainage at athletic fields

Phase 2 Interiors
  • Phase 2 elevator ready for testing
  • Continued balancing HVAC system
  • Started up all Phase 2 equipment

  • Area D
    • Completed flooding ACT ceiling tiles
    • Completed installation of wall tile
    • Completed installation of plinth at Stair 4
    • Completed installation of PLAM windowsills
    • Completed sealing concrete floors in Art rooms
    • Started installing rubber base
    • Started installaing carpet tile
    • Started Punch List

  • Area F
    • Continued installation of wall tile on Level 1
    • Completed flooding ACT ceilings on Levels 2 & 3
    • Completed installation of light fixtures
    • Started flooding ACT ceiling tiles on Level 1
    • Started installing rubber base
    • Started Punch List


Look-Ahead

April 2023 Look-Ahead


Phase 1
  • Complete April Break work-to-complete list
Phase 2 Site Work and Utilities
  • Continue raising grade via existing material
  • Continue final grading athletic fields
  • Continue installing drainage for athletic fields
  • Continue installation of sidewalks
Phase 2 Interiors
  • Complete balancing HVAC System
  • Phase 2 Elevator ready for testing
  • Start Commissioning

  • Area D
    • Complete installation of plinth at Stair 4
    • Complete installation of rubber base
    • Complete installation of carpet tile
    • Continue Punch List
    • Start final cleaning

  • Area F
    • Complete installing rubber base
    • Complete flooding ACT ceiling tile on Level 1
    • Continue Punch List
    • Start final cleaning